Frappe Cloud V2 launch plan

Engineering plan · 4 October 2026

Frappe Cloud V2 has three parts: Central (teams, billing, and resources), Atlas (virtual machines, or VMs), and Pilot (Frappe benches, apps, and sites). This plan lists the engineering work that must be done before the first public V2 offer.

Public launch does not turn off V1. Customers stay on V1 until their path to V2 works. That move is a separate project, listed near the end.

Size: S = under 1 week · M = 1–3 weeks · L = 1–2 months · XL = more than 2 months.

Priority: P0 = data, access, or money risk · P1 = needed for a good launch.

IDs: L-numbers come from the full delivery plan. Other IDs are new tasks added after the plan audit.

Milestones

Do the milestones in this order. A task can start early when its dependencies are done.

  1. Stop the risks. Fix access checks, backup choice, and backup status. Start site move, because it is the largest task.
  2. Make data and money safe. Restore, archive, billing correctness, invoices, and deploy checks.
  3. Complete the journey. Site creation choices, trial, site move, support access, and incidents.
  4. Prove it. Restore drills, payment gateway tests, region tests, and the launch check.

Dependency chains

L06 access checks → L25 support access
L09 backup choice → L10 backup status → L11 restore → L12 restore drills
B5 archive state → L08 trial expiry → L13 billing on stop and archive
L07 creation choices → L02 price preview

A. Access and security

IDTaskDone whenSizePriMS
L06Tighten Pilot access checks so each Central permission gives only the matching Pilot access.Access tests pass for every Central role and scope.MP01
L25Add support staff access to Pilot. Use the Central identity. Get approval from a team admin.Access is limited, expires, and every action is logged.Needs L06.LP13
A3Test 2FA setup, recovery codes, and forced 2FA in V2.V1 users with 2FA keep it after they move.SP12

B. Backup and restore

IDTaskDone whenSizePriMS
L09Ask for a backup mode at site creation: none, GFS, or another mode. Let the user change it in Pilot.No site is created without a recorded backup choice.MP01
L10Show local and offsite backup status separately. Retry and alert on failure.A failed offsite upload shows as failed and sends an alert.MP01
L11Add self-service restore of a selected backup. Take a backup before the restore.A user restores a site without support and sees progress.Needs L10.LP02
L12Run sampled restore drills. Publish recovery time and data loss window.Drill results exist for each offered region.Needs L11.LP04
B5Add an archive state in Pilot. Keep the last backup for the retention period.An archived site can be recovered until retention ends.MP02

C. Site creation and trial

IDTaskDone whenSizePriMS
L07Let the user choose app, region, Frappe version, VM size, and bucket. Reject bad combinations.All choices are required and validated.LP13
L02Show the VM price before creation.The price shows on the creation screen.Needs L07.SP13
L04Check app compatibility with version, country, and region before creation.An incompatible app cannot be selected.LP13
L08Trial: explain conversion, warn before expiry, stop unpaid sites, then archive them.Each trial step sends a notice.Needs B5.LP13

D. Billing and payments

IDTaskDone whenSizePriMS
L13Charge only for usable resources. Stop charges on failure, stop, and archive.Test cases pass for each state, including credit and refund.Needs L08.LP02
L14Enable invoice PDF and email. Add regional tax fields.Users download and receive invoices with tax details.MP12
L15Finish auto-recharge and stop-billing to match V1.Suspension and pending invoices work as in V1.LP12
L16Test Stripe and Razorpay in each offered region and currency.A live payment passes in each region and currency.MP14

E. Hosting reliability

IDTaskDone whenSizePriMS
L17Check disk, memory, and dependencies before deploy and update. Limit how long a task can run.A low-resource update stops before it starts. No task stays stuck. Fix-and-continue and rollback pass failure tests.LP02
L20Test private GitHub app install and update.Private repositories install, and credentials stay separate per team.LP13
L21Test domain and TLS changes, renewal, and fallback login.A broken primary domain does not block admin login.MP13
L22Test VM create, resize, snapshot, restore, and console in each offered region.All operations pass in each region and plan.LP14

F. Site move and releases

IDTaskDone whenSizePriMS
L18Add self-service site move between Pilot VMs and regions.A move shows status, checks the data, and can roll back.Start in milestone 1.XLP13
L19Give V1 release-group users a V2 equivalent, or keep them on V1.Each affected user has a working path.Only for affected users.XLP13

G. Customer journey and operations

IDTaskDone whenSizePriMS
L23One site list in Central with links to Pilot. Same task status in both. A support link on each resource.New users finish the core tasks in a usability test.LP13
L24Add fleet alerts, maintenance notices, an incident timeline, and RCA updates in the product.A test incident reaches affected users and shows in the timeline.LP13

Owned outside engineering

Engineering gives data for these tasks. Another team owns the result.

IDTaskOwner teamLaunch
L01Publish the supported offer: features, prices, regions, and gateways.ProductYes
L02Compare V1 and V2 bills and margin.Finance and ProductYes
L03Publish a plan matrix of verified protections and recovery targets.ComplianceYes
L05Keep a per-customer list of the V1 features each customer uses.Product and SupportYes
L26Partner program in V2. Partners stay on V1 until their flows work.Partner teamFor new V2 partners
L27Freemium on shared Pilot VMs.Freemium teamOnly if advertised

V1 migration (separate project)

IDTaskSize
M01List every active V1 account and its V2 destination.L
M02Move V1 shared sites to dedicated Pilot VMs, in tested batches.XL
M03Keep users on V1 when their workflow has no V2 equivalent.XL
M04Test update, backup, restore, domain, payment, and support for moved accounts.XL
MIG-5Add site import from an external site or backup file.L

Not for launch

Do not advertise these features at launch.

Launch check

Launch when all of these are true:

  1. Every launch task has a result that its owner approved.
  2. The paid and trial journeys pass end to end.
  3. The archive period, plans, and regions are published.
  4. Any advertised Freemium or partner path passes its own tests.

Sources

This plan is a short version of an internal delivery plan. That plan used a review of the Frappe Cloud V1 code (frappe/press, frappe/agent), the V2 code, open Press issues, and six months of support tickets. Sizes are estimates, not a schedule.